CaliforniaCaliforniaLawAB 2469
Data Centers: Water Use Disclosures
Bars cities and counties from approving permits for new or expanded data centers unless the applicant provides prescribed water use information and other conditions are met.
Signed by the governor; Chapter 436, Statutes of 2026Sep 21 7 weeks ago
- Body
- California Legislature
- Session
- 2025-2026
- Introduced
- Feb 20
- Takes effect
- Jan 1, 2027in 7 weeks
- Votes
- Assembly 61-14, Senate 28-9, Assembly concurrence 61-12
- Sponsors
- D (Democrat)Democrat
- Topics
- Data centers
Timeline
Sep 21 7 weeks ago
Aug 30 2 months ago
May 27 5 months ago
Feb 20 8 months ago
Sponsors
- D (Democrat)Assemblymember Papan
Related
CEQA: Data Centers and Geothermal Projects
Bars CEQA categorical exemptions for data center projects and lets the governor certify qualifying data center projects as environmental leadership development projects.
Data Centers: Rate Structures
Requires the Public Utilities Commission to assess rate structures so that data centers pay a reasonable share of transmission, distribution and procurement costs tied to their loads.
Data Centers: Reporting
Requires data center owners or operators to report information such as location, size, power usage effectiveness and onsite generator fuel use to the California Energy Commission.
Electricity: Data Centers
Requires each electrical corporation to file transmission, distribution and generation service tariffs for participating data center customers.
Water Resources: Data Centers
Requires data center operators to give their water supplier a good faith estimate of expected water use and water source before applying for a local business license or permit.
Data Centers: Labor: Electricity Rates
Would have required the Public Utilities Commission to establish a special electricity rate structure for data centers.
Water Resources: Data Centers
Would have required data center operators to give their water supplier an estimate of expected water use before applying for a local business license.
Electrical Corporations: Data Centers: Report
Authorizes the Public Utilities Commission to assess whether utility costs from new data center loads shift costs to other customers and to report its findings to the Legislature.
Change log
- AddedAdded to the list. Set by hand from the official record.Sep 27